Minsworth Sewage Treatment Works is an operational 9.7 MW sewage sludge digestion plant in Birmingham, generating since 1 April 2016. Planning permission was granted on 6 November 2013, 2 months after submission. Operator of record: Severn Trent Water.

9.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2016
Sewage Sludge Digestion
Technology
Severn Trent Water
Birmingham
Authority
England

Planning and build timeline

Application submitted29 August 2013
Permission granted6 November 2013
2 months after submission
Operational1 April 2016
29 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Birmingham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Minsworth Sewage Treatment Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
4002.7 km
Anaerobic Digestion · Operational
2.43.2 km
Landfill Gas · Operational
8.58.1 km
Landfill Gas · Operational
19.1 km
Advanced Conversion Technologies · Operational
10.39.8 km
EfW Incineration · Operational
3010 km
Solar Photovoltaics · Operational
511.2 km
Anaerobic Digestion · Operational
212.2 km

How big is Minsworth Sewage Treatment Works?

Minsworth Sewage Treatment Works has a recorded installed capacity of 9.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Minsworth Sewage Treatment Works?

REPD records the operator as Severn Trent Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Minsworth Sewage Treatment Works approved and built?

The application was submitted on 29 August 2013. Permission was granted on 6 November 2013, 2 months later. The site became operational on 1 April 2016, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6232.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode