Renewable sites › Binn Eco Park - Wind Farm
Binn Eco Park - Wind Farm
Binn Eco Park - Wind Farm is operational in Perth and Kinross with a recorded capacity of 10 MW, and has been generating since 2020-01-01.
Planning and build timeline
| Application submitted | 2014-11-25 |
| Permission granted | 2015-08-20 9 months after submission |
| Operational | 2020-01-01 52 months after consent |
Perth and Kinross’s record on onshore wind
Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Binn Farm AD (extension) Anaerobic Digestion · Operational | 1.5 | 0.5 km |
Binn Landfill Landfill Gas · Operational | 1.9 | 0.5 km |
Binn Eco Park - EfW EfW Incineration · Under Construction | 7.3 | 1 km |
Jamesfield Organic Centre - Battery Storage Battery · Operational | 49 | 5 km |
Lochelbank Wind Farm II Wind Onshore · Operational | 9.6 | 6.4 km |
Errol Estate Solar Photovoltaics · Operational | 13 | 7.6 km |
Perth Wastewater Treatment Works Solar Photovoltaics · Operational | 0.4 | 9.2 km |
Perth Wastewater Treatment Works (Extension) Battery · Operational | — | 9.3 km |
How big is Binn Eco Park - Wind Farm?
Binn Eco Park - Wind Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Binn Eco Park - Wind Farm?
REPD records the operator as Binn Eco Park. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Binn Eco Park - Wind Farm approved and built?
The application was submitted on 2014-11-25. Permission was granted on 2015-08-20, 9 months later. The site became operational on 2020-01-01, 52 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4817.