Bilsborrow Solar Farm is operational in Wyre with a recorded capacity of 5 MW, and has been generating since 2017-03-30.
Planning and build timeline
| Application submitted | 2015-03-23 |
| Permission granted | 2015-06-15 3 months after submission |
| Operational | 2017-03-30 21 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wyre’s record on solar
Wyre has decided 9 solar farms and approved 100%, taking a median of 4.3 months. See every solar farm decision in Wyre →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Westfield Farm Solar Photovoltaics · Operational | 5 | 3 km |
Dewlay Cheese Wind Turbine Wind Onshore · Operational | 2 | 5 km |
Oakfield Farm - extension Solar Photovoltaics · Operational | 1.7 | 8.7 km |
Oakfield Farm Solar Photovoltaics · Operational | 5 | 8.9 km |
Brookhouse Mill Solar Photovoltaics · Operational | 0.3 | 9 km |
Orchard End Wind Onshore · Operational | 4 | 9.2 km |
Fell View Farm (Phase 2) Solar Photovoltaics · Operational | 2.9 | 10.8 km |
Clifton Marsh Energy Landfill Gas · Operational | 3.3 | 10.8 km |
How big is Bilsborrow Solar Farm?
Bilsborrow Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bilsborrow Solar Farm?
REPD records the operator as Greencoat Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bilsborrow Solar Farm approved and built?
The application was submitted on 2015-03-23. Permission was granted on 2015-06-15, 3 months later. The site became operational on 2017-03-30, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5163.