Fell View Farm (Phase 2) is an operational 2.9 MW solar farm in Preston, generating since 15 March 2016. Planning permission was granted on 4 August 2015, 4 months after submission. Operator of record: Anesco.

2.9 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2016
Solar Photovoltaics
Technology
Anesco
Preston
Authority
England

Planning and build timeline

Application submitted13 April 2015
Permission granted4 August 2015
4 months after submission
Operational15 March 2016
7 months after consent

Screening a site of your own?

RedlineUK · £39

Preston approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Fell View Farm (Phase 2)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Preston’s record on solar

Preston has decided 10 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Preston

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.20.2 km
Solar Photovoltaics · Operational
23.8 km
Solar Photovoltaics · Operational
0.36.9 km
Landfill Gas · Operational
2.310.2 km
Solar Photovoltaics · Operational
510.8 km
Solar Photovoltaics · Operational
0.311.9 km
Battery · Under Construction
512.2 km
Solar Photovoltaics · Operational
1.712.3 km

How big is Fell View Farm (Phase 2)?

Fell View Farm (Phase 2) has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fell View Farm (Phase 2)?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fell View Farm (Phase 2) approved and built?

The application was submitted on 13 April 2015. Permission was granted on 4 August 2015, 4 months later. The site became operational on 15 March 2016, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5261.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode