Renewable sites › Barnfield Solar Park
Barnfield Solar Park
Barnfield Solar Park is an operational 2.5 MW solar farm in Swindon, generating since 10 December 2018. Planning permission was granted on 25 October 2016, 2 months after submission. Operator of record: Public Power Solutions.
Planning and build timeline
| Application submitted | 26 August 2016 |
| Permission granted | 25 October 2016 2 months after submission |
| Operational | 10 December 2018 25 months after consent |
Screening a site of your own?
Swindon approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Barnfield Solar Park’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Swindon’s record on solar
Swindon has decided 35 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Swindon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 6 | 0.1 km |
Anaerobic Digestion · Operational | 1.2 | 0.7 km |
Battery · Operational | 49.9 | 2.3 km |
Solar Photovoltaics · Under Construction | 0.91 | 3.8 km |
Solar Photovoltaics · Operational | 4.8 | 4.3 km |
Solar Photovoltaics · Operational | 5 | 4.4 km |
Landfill Gas · Operational | 3 | 4.7 km |
Solar Photovoltaics · Operational | 5 | 5.4 km |
How big is Barnfield Solar Park?
Barnfield Solar Park has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barnfield Solar Park?
REPD records the operator as Public Power Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barnfield Solar Park approved and built?
The application was submitted on 26 August 2016. Permission was granted on 25 October 2016, 2 months later. The site became operational on 10 December 2018, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6069.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode