Barnfield Solar Park

Barnfield Solar Park is an operational 2.5 MW solar farm in Swindon, generating since 10 December 2018. Planning permission was granted on 25 October 2016, 2 months after submission. Operator of record: Public Power Solutions.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 10 December 2018
Solar Photovoltaics
Technology
Public Power Solutions
Swindon
Authority
England

Planning and build timeline

Application submitted26 August 2016
Permission granted25 October 2016
2 months after submission
Operational10 December 2018
25 months after consent

Screening a site of your own?

RedlineUK · £39

Swindon approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barnfield Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Swindon’s record on solar

Swindon has decided 35 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Swindon

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
60.1 km
Anaerobic Digestion · Operational
1.20.7 km
Battery · Operational
49.92.3 km
Solar Photovoltaics · Under Construction
0.913.8 km
Solar Photovoltaics · Operational
4.84.3 km
Solar Photovoltaics · Operational
54.4 km
Landfill Gas · Operational
34.7 km
Solar Photovoltaics · Operational
55.4 km

How big is Barnfield Solar Park?

Barnfield Solar Park has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barnfield Solar Park?

REPD records the operator as Public Power Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barnfield Solar Park approved and built?

The application was submitted on 26 August 2016. Permission was granted on 25 October 2016, 2 months later. The site became operational on 10 December 2018, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6069.