Mannington Battery Storage Plant

Mannington Battery Storage Plant is an operational 49.9 MW battery storage site in Swindon, generating since 1 October 2021. Planning permission was granted on 7 December 2018, 13 months after submission. Operator of record: Still Waters Green Technology.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 2021
Battery
Technology
Still Waters Green Technology
Swindon
Authority
England

Planning and build timeline

Application submitted21 November 2017
Permission granted7 December 2018
13 months after submission
Operational1 October 2021
34 months after consent

Screening a site of your own?

RedlineUK · £39

Swindon approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Mannington Battery Storage Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Swindon’s record on battery storage

Swindon has decided 6 battery storage schemes and approved 100%, taking a median of 6.2 months. See every battery storage scheme decision in Swindon

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.21.7 km
Solar Photovoltaics · Operational
4.82.2 km
Solar Photovoltaics · Operational
2.52.3 km
Battery · Under Construction
62.3 km
Solar Photovoltaics · Operational
10.53.6 km
Solar Photovoltaics · Operational
54.1 km
Solar Photovoltaics · Operational
124.7 km
Solar Photovoltaics · Operational
414.8 km

How big is Mannington Battery Storage Plant?

Mannington Battery Storage Plant has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mannington Battery Storage Plant?

REPD records the operator as Still Waters Green Technology. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mannington Battery Storage Plant approved and built?

The application was submitted on 21 November 2017. Permission was granted on 7 December 2018, 13 months later. The site became operational on 1 October 2021, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7024.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode