Novarly ParcelRenewable sites

Renewable sitesChapel Farm Landfill

Chapel Farm Landfill

Chapel Farm Landfill is operational in Swindon with a recorded capacity of 3 MW, and has been generating since 2001-01-15.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-01-15
Landfill Gas
Technology
HILLS MINERALS & WASTE LTD
Swindon
Authority
England

Planning and build timeline

Application submitted1999-04-27
Permission granted1999-07-12
2 months after submission
Operational2001-01-15
18 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Chapel Farm
Solar Photovoltaics · Operational
50.6 km
Arkwright Road, Groundwell Industrial Estate - Solar Panels
Solar Photovoltaics · Under Construction
0.913.1 km
Water Eaton Farm / Port Farm
Solar Photovoltaics · Operational
34.83.1 km
Castle Eaton Farm
Solar Photovoltaics · Operational
17.83.9 km
Stanton solar park
Solar Photovoltaics · Operational
54 km
Brindley Close (Extension)
Battery · Under Construction
64.7 km
Barnfield Solar Park
Solar Photovoltaics · Operational
2.54.7 km
B&Q Swindon DC
Solar Photovoltaics · Operational
2.54.9 km

How big is Chapel Farm Landfill?

Chapel Farm Landfill has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chapel Farm Landfill?

REPD records the operator as HILLS MINERALS & WASTE LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chapel Farm Landfill approved and built?

The application was submitted on 1999-04-27. Permission was granted on 1999-07-12, 2 months later. The site became operational on 2001-01-15, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 590.