Renewable sites › Swindon Sewerage Treatment Works
Swindon Sewerage Treatment Works
Swindon Sewerage Treatment Works is operational in Swindon with a recorded capacity of 1.2 MW, and has been generating since 2016-06-15.
Planning and build timeline
| Application submitted | 2015-04-01 |
| Permission granted | not recorded |
| Operational | 2016-06-15 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Barnfield Solar Park Solar Photovoltaics · Operational | 2.5 | 0.7 km |
Brindley Close (Extension) Battery · Under Construction | 6 | 0.8 km |
Mannington Battery Storage Plant Battery · Operational | 49.9 | 1.7 km |
Common Farm Solar Photovoltaics · Operational | 4.8 | 3.6 km |
Arkwright Road, Groundwell Industrial Estate - Solar Panels Solar Photovoltaics · Under Construction | 0.91 | 4.1 km |
Lower Basset Down Farm Solar Photovoltaics · Operational | 10.5 | 5 km |
Chapel Farm Solar Photovoltaics · Operational | 5 | 5.1 km |
Wickfield Farm Solar Photovoltaics · Operational | 5 | 5.2 km |
How big is Swindon Sewerage Treatment Works?
Swindon Sewerage Treatment Works has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Swindon Sewerage Treatment Works?
REPD records the operator as Thames Water Utilities. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Swindon Sewerage Treatment Works approved and built?
The application was submitted on 2015-04-01. REPD does not record a grant date. The site became operational on 2016-06-15.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6489.