Barley Wood Farm Lane is an operational 5.4 MW solar farm in East Hampshire, generating since 20 March 2015. Planning permission was granted on 31 March 2014, 4 months after submission. Operator of record: Lightsource Renewable Energy.

5.4 MW
Capacity
as recorded in REPD
Operational
Status
since 20 March 2015
Solar Photovoltaics
Technology
Lightsource Renewable Energy
East Hampshire
Authority
England

Planning and build timeline

Application submitted9 December 2013
Permission granted31 March 2014
4 months after submission
Operational20 March 2015
12 months after consent

Screening a site of your own?

RedlineUK · £39

East Hampshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barley Wood Farm Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Hampshire’s record on solar

East Hampshire has decided 16 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in East Hampshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.372.8 km
Solar Photovoltaics · Operational
113.7 km
Solar Photovoltaics · Operational
113.7 km
Solar Photovoltaics · Operational
1210.6 km
Solar Photovoltaics · Operational
112.2 km
Solar Photovoltaics · Operational
1212.6 km
Anaerobic Digestion · Under Construction
12.7 km
Solar Photovoltaics · Operational
512.8 km

How big is Barley Wood Farm Lane?

Barley Wood Farm Lane has a recorded installed capacity of 5.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barley Wood Farm Lane?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barley Wood Farm Lane approved and built?

The application was submitted on 9 December 2013. Permission was granted on 31 March 2014, 4 months later. The site became operational on 20 March 2015, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1474.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode