Renewable sites › Elginny Hill
Elginny Hill
Elginny Hill is operational in Mid and East Antrim with a recorded capacity of 22 MW, and has been generating since 2018-03-15.
Planning and build timeline
| Application submitted | 2011-03-15 |
| Permission granted | 2014-11-13 44 months after submission |
| Operational | 2018-03-15 40 months after consent |
Mid and East Antrim’s record on onshore wind
Mid and East Antrim has decided 21 onshore wind schemes and approved 81%, taking a median of 14.6 months. See every onshore wind scheme decision in Mid and East Antrim →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rathsherry Wind Onshore · Operational | 21 | 2.4 km |
Ballymena Wind Park Limited Wind Onshore · Operational | 4.7 | 6.5 km |
The Michelin Tyre Factory - Ballymena Wind Onshore · Operational | 4.6 | 6.7 km |
Ballygarvey Road Solar Photovoltaics · Operational | 13 | 6.7 km |
Tully Quarry Anaerobic Digestion · Operational | 3 | 10.6 km |
Gruig Wind Farm Wind Onshore · Operational | 25 | 11.3 km |
Corkey Wind Farm Extension Wind Onshore · Operational | 2.5 | 13.6 km |
Corkey Wind Farm Wind Onshore · Operational | 5 | 13.8 km |
How big is Elginny Hill?
Elginny Hill has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Elginny Hill?
REPD records the operator as Brookfields (Antrim Wind Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Elginny Hill approved and built?
The application was submitted on 2011-03-15. Permission was granted on 2014-11-13, 44 months later. The site became operational on 2018-03-15, 40 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4563.