Renewable sites › Altahullion Phase II
Altahullion Phase II
Altahullion Phase II is operational in Causeway Coast and Glens with a recorded capacity of 11.7 MW, and has been generating since 2007-09-01.
Planning and build timeline
| Application submitted | 2004-11-22 |
| Permission granted | 2006-04-06 16 months after submission |
| Operational | 2007-09-01 17 months after consent |
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Slieve Kirk (formerly Glenconway) Wind Onshore · Operational | 18.4 | 2 km |
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) Wind Onshore · Operational | 27.6 | 2.3 km |
Altahullion Wind Onshore · Operational | 26 | 2.4 km |
Monnaboy Wind Farm Wind Onshore · Operational | 12 | 8.7 km |
Brockaghboy Wind Farm - extension Wind Onshore · Operational | 10 | 11.5 km |
Rigged Hill Wind Farm Wind Onshore · Operational | 5 | 12.9 km |
Craiggore windfarm Wind Onshore · Operational | 23.5 | 13 km |
Dunmore Wind Onshore · Operational | 21 | 13.1 km |
How big is Altahullion Phase II?
Altahullion Phase II has a recorded installed capacity of 11.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Altahullion Phase II?
REPD records the operator as B9 Energy / RES. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Altahullion Phase II approved and built?
The application was submitted on 2004-11-22. Permission was granted on 2006-04-06, 16 months later. The site became operational on 2007-09-01, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3244.
Novarly Parcel · official public data, read properly · parcel.novarly.com