Altahullion Phase II

Altahullion Phase II is an operational 11.7 MW onshore wind farm in Causeway Coast and Glens, generating since 1 September 2007. Planning permission was granted on 6 April 2006, 16 months after submission. Operator of record: B9 Energy / RES.

11.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2007
Wind Onshore
Technology
B9 Energy / RES
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted22 November 2004
Permission granted6 April 2006
16 months after submission
Operational1 September 2007
17 months after consent

Screening a site of your own?

RedlineUK · £39

Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Altahullion Phase II’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
18.42 km
Wind Onshore · Operational
27.62.3 km
Wind Onshore · Operational
262.4 km
Wind Onshore · Operational
128.7 km
Wind Onshore · Operational
1011.5 km
Wind Onshore · Operational
512.9 km
Wind Onshore · Operational
23.513 km
Wind Onshore · Operational
2113.1 km

How big is Altahullion Phase II?

Altahullion Phase II has a recorded installed capacity of 11.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Altahullion Phase II?

REPD records the operator as B9 Energy / RES. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Altahullion Phase II approved and built?

The application was submitted on 22 November 2004. Permission was granted on 6 April 2006, 16 months later. The site became operational on 1 September 2007, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3244.