Rigged Hill Wind Farm
Rigged Hill Wind Farm is an operational 5 MW onshore wind farm in Causeway Coast and Glens, generating since 1 November 1994. Planning permission was granted on 1 July 1994, 7 months after submission. Operator of record: B9 Energy Services Ltd/ ScottishPower Renewables.
Planning and build timeline
| Application submitted | 19 November 1993 |
| Permission granted | 1 July 1994 7 months after submission |
| Operational | 1 November 1994 4 months after consent |
Screening a site of your own?
Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Rigged Hill Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 23.5 | 3.2 km |
Wind Onshore · Operational | 37.5 | 5.8 km |
Wind Onshore · Operational | 21 | 6.8 km |
Wind Onshore · Operational | 42 | 7.9 km |
Wind Onshore · Operational | 11.7 | 12.9 km |
Wind Onshore · Operational | 10 | 14 km |
Wind Onshore · Operational | 18.4 | 14.4 km |
Wind Onshore · Operational | 27.6 | 14.9 km |
How big is Rigged Hill Wind Farm?
Rigged Hill Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rigged Hill Wind Farm?
REPD records the operator as B9 Energy Services Ltd/ ScottishPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rigged Hill Wind Farm approved and built?
The application was submitted on 19 November 1993. Permission was granted on 1 July 1994, 7 months later. The site became operational on 1 November 1994, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3112.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode