Renewable sites › Craiggore windfarm
Craiggore windfarm
Craiggore windfarm is an operational 23.5 MW onshore wind farm in Causeway Coast and Glens. Planning permission was granted on 5 March 2015, 29 months after submission. Operator of record: Renewable Energy Systems (RES).
Planning and build timeline
| Application submitted | 15 October 2012 |
| Permission granted | 5 March 2015 29 months after submission |
| Operational | not recorded |
Screening a site of your own?
Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Craiggore windfarm’s recorded coordinate — swap in your own postcode or coordinates.
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 37.5 | 2.8 km |
Wind Onshore · Operational | 5 | 3.2 km |
Wind Onshore · Operational | 21 | 9.9 km |
Wind Onshore · Operational | 42 | 11 km |
Wind Onshore · Operational | 10 | 11.6 km |
Wind Onshore · Operational | 11.7 | 13 km |
Wind Onshore · Operational | 18.4 | 14.8 km |
How big is Craiggore windfarm?
Craiggore windfarm has a recorded installed capacity of 23.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Craiggore windfarm?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Craiggore windfarm approved and built?
The application was submitted on 15 October 2012. Permission was granted on 5 March 2015, 29 months later. REPD does not record an operational date.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4297.
Novarly Parcel · official public data, read properly · parcel.novarly.com