Novarly ParcelRenewable sites

Renewable sitesDunmore

Dunmore

Dunmore is an operational 21 MW onshore wind farm in Causeway Coast and Glens, generating since 25 April 2013. Planning permission was granted on 29 October 2010, 35 months after submission. Operator of record: TCI Renewables.

21 MW
Capacity
as recorded in REPD
Operational
Status
since 25 April 2013
Wind Onshore
Technology
TCI Renewables
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted12 December 2007
Permission granted29 October 2010
35 months after submission
Operational25 April 2013
30 months after consent

Screening a site of your own?

RedlineUK · £39

Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dunmore’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
421.3 km
Wind Onshore · Operational
56.8 km
Wind Onshore · Operational
23.59.9 km
Wind Onshore · Operational
37.512.6 km
Wind Onshore · Operational
11.713.1 km
Wind Onshore · Operational
18.413.7 km
Wind Onshore · Operational
27.614.4 km

How big is Dunmore?

Dunmore has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dunmore?

REPD records the operator as TCI Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dunmore approved and built?

The application was submitted on 12 December 2007. Permission was granted on 29 October 2010, 35 months later. The site became operational on 25 April 2013, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3969.