Renewable sitesDunmore

Dunmore

Dunmore is operational in Causeway Coast and Glens with a recorded capacity of 21 MW, and has been generating since 2013-04-25.

21 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-04-25
Wind Onshore
Technology
TCI Renewables
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted2007-12-12
Permission granted2010-10-29
35 months after submission
Operational2013-04-25
30 months after consent

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Windyhill Road (Dunbeg) Wind Farm
Wind Onshore · Operational
421.3 km
Rigged Hill Wind Farm
Wind Onshore · Operational
56.8 km
Craiggore windfarm
Wind Onshore · Operational
23.59.9 km
Brockaghboy Wind Farm
Wind Onshore · Operational
37.512.6 km
Altahullion Phase II
Wind Onshore · Operational
11.713.1 km
Slieve Kirk (formerly Glenconway)
Wind Onshore · Operational
18.413.7 km
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)
Wind Onshore · Operational
27.614.4 km

How big is Dunmore?

Dunmore has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dunmore?

REPD records the operator as TCI Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dunmore approved and built?

The application was submitted on 2007-12-12. Permission was granted on 2010-10-29, 35 months later. The site became operational on 2013-04-25, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3969.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council