Renewable sites › Dunmore
Dunmore
Dunmore is an operational 21 MW onshore wind farm in Causeway Coast and Glens, generating since 25 April 2013. Planning permission was granted on 29 October 2010, 35 months after submission. Operator of record: TCI Renewables.
Planning and build timeline
| Application submitted | 12 December 2007 |
| Permission granted | 29 October 2010 35 months after submission |
| Operational | 25 April 2013 30 months after consent |
Screening a site of your own?
Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dunmore’s recorded coordinate — swap in your own postcode or coordinates.
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 42 | 1.3 km |
Wind Onshore · Operational | 5 | 6.8 km |
Wind Onshore · Operational | 23.5 | 9.9 km |
Wind Onshore · Operational | 37.5 | 12.6 km |
Wind Onshore · Operational | 11.7 | 13.1 km |
Wind Onshore · Operational | 18.4 | 13.7 km |
Wind Onshore · Operational | 27.6 | 14.4 km |
How big is Dunmore?
Dunmore has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dunmore?
REPD records the operator as TCI Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dunmore approved and built?
The application was submitted on 12 December 2007. Permission was granted on 29 October 2010, 35 months later. The site became operational on 25 April 2013, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3969.