Dunmore
Dunmore is operational in Causeway Coast and Glens with a recorded capacity of 21 MW, and has been generating since 2013-04-25.
Planning and build timeline
| Application submitted | 2007-12-12 |
| Permission granted | 2010-10-29 35 months after submission |
| Operational | 2013-04-25 30 months after consent |
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Windyhill Road (Dunbeg) Wind Farm Wind Onshore · Operational | 42 | 1.3 km |
Rigged Hill Wind Farm Wind Onshore · Operational | 5 | 6.8 km |
Craiggore windfarm Wind Onshore · Operational | 23.5 | 9.9 km |
Brockaghboy Wind Farm Wind Onshore · Operational | 37.5 | 12.6 km |
Altahullion Phase II Wind Onshore · Operational | 11.7 | 13.1 km |
Slieve Kirk (formerly Glenconway) Wind Onshore · Operational | 18.4 | 13.7 km |
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) Wind Onshore · Operational | 27.6 | 14.4 km |
How big is Dunmore?
Dunmore has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dunmore?
REPD records the operator as TCI Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dunmore approved and built?
The application was submitted on 2007-12-12. Permission was granted on 2010-10-29, 35 months later. The site became operational on 2013-04-25, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3969.