Renewable sites › Brockaghboy Wind Farm - extension
Brockaghboy Wind Farm - extension
Brockaghboy Wind Farm - extension is operational in Causeway Coast and Glens with a recorded capacity of 10 MW, and has been generating since 2017-09-01.
Planning and build timeline
| Application submitted | 2014-06-25 |
| Permission granted | 2015-10-27 16 months after submission |
| Operational | 2017-09-01 22 months after consent |
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brockaghboy Wind Farm Wind Onshore · Operational | 37.5 | 11.3 km |
Altahullion Phase II Wind Onshore · Operational | 11.7 | 11.5 km |
Craiggore windfarm Wind Onshore · Operational | 23.5 | 11.6 km |
Altahullion Wind Onshore · Operational | 26 | 12.7 km |
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) Wind Onshore · Operational | 27.6 | 13.3 km |
Slieve Kirk (formerly Glenconway) Wind Onshore · Operational | 18.4 | 13.4 km |
Rigged Hill Wind Farm Wind Onshore · Operational | 5 | 14 km |
Draperstown (Brackagh) Wind Farm Wind Onshore · Operational | 6 | 14.2 km |
How big is Brockaghboy Wind Farm - extension?
Brockaghboy Wind Farm - extension has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brockaghboy Wind Farm - extension?
REPD records the operator as Greencoat. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brockaghboy Wind Farm - extension approved and built?
The application was submitted on 2014-06-25. Permission was granted on 2015-10-27, 16 months later. The site became operational on 2017-09-01, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2888.