Withernwick extension

Withernwick extension is operational in East Riding of Yorkshire with a recorded capacity of 8.2 MW, and has been generating since 2019-08-01.

8.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2019-08-01
Wind Onshore
Technology
Energiekontor UK
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2014-06-24
Permission granted2016-12-19
30 months after submission
Operational2019-08-01
31 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Withernwick
Wind Onshore · Operational
181.6 km
Hull Biomass Plant (Tansterne power station)
Biomass (dedicated) · Operational
224.6 km
Hull Solar Farm
Solar Photovoltaics · Under Construction
25.710.8 km
Carlam Hill Education CIC
Solar Photovoltaics · Operational
511.4 km
Burton Pidsea (Wadworth Hill) Wind Farm
Wind Onshore · Operational
10.212.7 km
The Limes Wind Turbines
Wind Onshore · Operational
1.712.8 km
Hall Farm Routh
Wind Onshore · Operational
24.612.9 km
Roos Wind Farm (Resubmission)
Wind Onshore · Operational
17.113.5 km

How big is Withernwick extension?

Withernwick extension has a recorded installed capacity of 8.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Withernwick extension?

REPD records the operator as Energiekontor UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Withernwick extension approved and built?

The application was submitted on 2014-06-24. Permission was granted on 2016-12-19, 30 months later. The site became operational on 2019-08-01, 31 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4432.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council