Novarly ParcelRenewable sites

Renewable sitesRoos Wind Farm (Resubmission)

Roos Wind Farm (Resubmission)

Roos Wind Farm (Resubmission) is operational in East Riding of Yorkshire with a recorded capacity of 17.1 MW, and has been generating since 2013-04-02.

17.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-04-02
Wind Onshore
Technology
Renewable Energy Systems (RES)
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2009-01-20
Permission granted2010-05-13
16 months after submission
Operational2013-04-02
35 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Tedder Hill Wind cluster
Wind Onshore · Operational
7.52.8 km
Burton Pidsea (Wadworth Hill) Wind Farm
Wind Onshore · Operational
10.22.9 km
Redhall Industrial Estate
Solar Photovoltaics · Operational
56.1 km
Far Marsh Farm
Wind Onshore · Operational
7.58.8 km
Hull Biomass Plant (Tansterne power station)
Biomass (dedicated) · Operational
229 km
The Limes Wind Turbines
Wind Onshore · Operational
1.710.9 km
Saltend Wind Turbine
Wind Onshore · Operational
1.311 km
Hull Solar Farm
Solar Photovoltaics · Under Construction
25.711.5 km

How big is Roos Wind Farm (Resubmission)?

Roos Wind Farm (Resubmission) has a recorded installed capacity of 17.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Roos Wind Farm (Resubmission)?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Roos Wind Farm (Resubmission) approved and built?

The application was submitted on 2009-01-20. Permission was granted on 2010-05-13, 16 months later. The site became operational on 2013-04-02, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3835.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council