Novarly ParcelRenewable sites

Renewable sitesRoos Wind Farm (Resubmission)

Roos Wind Farm (Resubmission)

Roos Wind Farm (Resubmission) is an operational 17.1 MW onshore wind farm in East Riding of Yorkshire, generating since 2 April 2013. Planning permission was granted on 13 May 2010, 16 months after submission. Operator of record: Renewable Energy Systems (RES).

17.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2 April 2013
Wind Onshore
Technology
Renewable Energy Systems (RES)
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted20 January 2009
Permission granted13 May 2010
16 months after submission
Operational2 April 2013
35 months after consent

Screening a site of your own?

RedlineUK · £39

East Riding of Yorkshire approves 82% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Roos Wind Farm (Resubmission)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
7.52.8 km
Wind Onshore · Operational
10.22.9 km
Solar Photovoltaics · Operational
56.1 km
Wind Onshore · Operational
7.58.8 km
Biomass (dedicated) · Operational
229 km
Wind Onshore · Operational
1.710.9 km
Wind Onshore · Operational
1.311 km
Solar Photovoltaics · Under Construction
25.711.5 km

How big is Roos Wind Farm (Resubmission)?

Roos Wind Farm (Resubmission) has a recorded installed capacity of 17.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Roos Wind Farm (Resubmission)?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Roos Wind Farm (Resubmission) approved and built?

The application was submitted on 20 January 2009. Permission was granted on 13 May 2010, 16 months later. The site became operational on 2 April 2013, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3835.