Withernwick is an operational 18 MW onshore wind farm in East Riding of Yorkshire, generating since 19 March 2013. Planning permission was granted on 2 September 2008, 5 months after submission. Operator of record: Energiekontor UK.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 19 March 2013
Wind Onshore
Technology
Energiekontor UK
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted4 April 2008
Permission granted2 September 2008
5 months after submission
Operational19 March 2013
55 months after consent

Screening a site of your own?

RedlineUK · £39

East Riding of Yorkshire approves 82% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Withernwick’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.21.6 km
Biomass (dedicated) · Operational
223.4 km
Solar Photovoltaics · Under Construction
25.79.2 km
Solar Photovoltaics · Operational
510.3 km
Wind Onshore · Operational
1.711.2 km
Wind Onshore · Operational
10.211.4 km
Wind Onshore · Operational
1.312 km
Wind Onshore · Operational
17.112.5 km

How big is Withernwick?

Withernwick has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Withernwick?

REPD records the operator as Energiekontor UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Withernwick approved and built?

The application was submitted on 4 April 2008. Permission was granted on 2 September 2008, 5 months later. The site became operational on 19 March 2013, 55 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3987.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode