Renewable sites › Royston Solar Farm (Phase 1) (a)
Royston Solar Farm (Phase 1) (a)
Royston Solar Farm (Phase 1) (a) is operational in South Cambridgeshire with a recorded capacity of 5 MW, and has been generating since 2016-01-29.
Planning and build timeline
| Application submitted | 2014-07-01 |
| Permission granted | 2014-10-29 4 months after submission |
| Operational | 2016-01-29 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Cambridgeshire’s record on solar
South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bassingbourn Solar Farm Solar Photovoltaics · Operational | 14.4 | 1.5 km |
Munceys Farm Solar Photovoltaics · Operational | 31.6 | 2.3 km |
Bury Lane Fruit Farm Solar Photovoltaics · Operational | 24 | 2.3 km |
Hatch Penn Farm PV Solar Photovoltaics · Operational | 1 | 4.9 km |
Black Peak Farm Solar Photovoltaics · Operational | 31.8 | 5.1 km |
Hoback Farm Solar Photovoltaics · Operational | 13.1 | 6 km |
Vine Farm Solar Park Solar Photovoltaics · Operational | 45 | 6.1 km |
Wisbridge Farm Solar Photovoltaics · Operational | 9.3 | 6.4 km |
How big is Royston Solar Farm (Phase 1) (a)?
Royston Solar Farm (Phase 1) (a) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Royston Solar Farm (Phase 1) (a)?
REPD records the operator as Canadian Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Royston Solar Farm (Phase 1) (a) approved and built?
The application was submitted on 2014-07-01. Permission was granted on 2014-10-29, 4 months later. The site became operational on 2016-01-29, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2202.