Renewable sites › Bury Lane Fruit Farm
Bury Lane Fruit Farm
Bury Lane Fruit Farm is an operational 24 MW solar farm in South Cambridgeshire, generating since 19 December 2014. Planning permission was granted on 12 May 2014, 5 months after submission. Operator of record: Vortex (formerly Sun Edison).
Planning and build timeline
| Application submitted | 18 December 2013 |
| Permission granted | 12 May 2014 5 months after submission |
| Operational | 19 December 2014 7 months after consent |
Screening a site of your own?
South Cambridgeshire approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bury Lane Fruit Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Cambridgeshire’s record on solar
South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 31.6 | 1.7 km |
Solar Photovoltaics · Operational | 5 | 2.3 km |
Solar Photovoltaics · Operational | 31.8 | 3.2 km |
Solar Photovoltaics · Operational | 14.4 | 3.2 km |
Solar Photovoltaics · Operational | 13.1 | 4.9 km |
Solar Photovoltaics · Operational | 45 | 6 km |
Solar Photovoltaics · Operational | 1 | 6.6 km |
Solar Photovoltaics · Operational | 0.4 | 6.8 km |
How big is Bury Lane Fruit Farm?
Bury Lane Fruit Farm has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bury Lane Fruit Farm?
REPD records the operator as Vortex (formerly Sun Edison). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bury Lane Fruit Farm approved and built?
The application was submitted on 18 December 2013. Permission was granted on 12 May 2014, 5 months later. The site became operational on 19 December 2014, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2372.
Novarly Parcel · official public data, read properly · parcel.novarly.com