Novarly ParcelRenewable sites

Renewable sitesBarry Docks

Barry Docks

Barry Docks is an operational 10 MW advanced conversion plant in Vale of Glamorgan, generating since 15 April 2018. Planning permission was granted on 31 July 2015, 6 months after submission. Operator of record: Sunrise Renewables.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 15 April 2018
Advanced Conversion Technologies
Technology
Sunrise Renewables
Vale of Glamorgan
Authority
Wales

Planning and build timeline

Application submitted12 February 2015
Permission granted31 July 2015
6 months after submission
Operational15 April 2018
32 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Vale of Glamorgan: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barry Docks’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.6 km
Solar Photovoltaics · Operational
4.50.6 km
Solar Photovoltaics · Operational
52.7 km
Solar Photovoltaics · Operational
73.9 km
Solar Photovoltaics · Operational
54.3 km
Solar Photovoltaics · Operational
7.55.2 km
Solar Photovoltaics · Operational
66.4 km
Solar Photovoltaics · Operational
57.5 km

How big is Barry Docks?

Barry Docks has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barry Docks?

REPD records the operator as Sunrise Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barry Docks approved and built?

The application was submitted on 12 February 2015. Permission was granted on 31 July 2015, 6 months later. The site became operational on 15 April 2018, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5088.