Renewable sitesBiglis Farm

Biglis Farm

Biglis Farm is operational in Vale of Glamorgan with a recorded capacity of 5 MW, and has been generating since 2016-03-31.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-31
Solar Photovoltaics
Technology
Conergy West Sussex
Vale of Glamorgan
Authority
Wales

Planning and build timeline

Application submitted2015-05-28
Permission granted2015-10-02
4 months after submission
Operational2016-03-31
6 months after consent

Vale of Glamorgan’s record on solar

Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan

Other built sites within 15 km

SiteMWDistance
Barry Docks
Advanced Conversion Technologies · Operational
102.7 km
Port of Barry - Site 1
Solar Photovoltaics · Operational
4.53.2 km
Port of Barry - Site 2
Solar Photovoltaics · Operational
53.2 km
Weycock Road
Solar Photovoltaics · Operational
74.8 km
Woden Park
Solar Photovoltaics · Operational
55 km
Cwm Derwyn Farm
Solar Photovoltaics · Operational
55.3 km
Sutton Mawr Farm
Solar Photovoltaics · Operational
7.56.1 km
Whitton Mawr
Solar Photovoltaics · Operational
66.2 km

How big is Biglis Farm?

Biglis Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Biglis Farm?

REPD records the operator as Conergy West Sussex. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Biglis Farm approved and built?

The application was submitted on 2015-05-28. Permission was granted on 2015-10-02, 4 months later. The site became operational on 2016-03-31, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5289.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council