West Bradley Farm is an operational 1.5 MW solar farm in Mid Devon, generating since 3 August 2012. Planning permission was granted on 18 May 2012, 2 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 16 March 2012 |
| Permission granted | 18 May 2012 2 months after submission |
| Operational | 3 August 2012 3 months after consent |
Screening a site of your own?
Mid Devon approves 80% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with West Bradley Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Mid Devon’s record on solar
Mid Devon has decided 30 solar farms and approved 80%, taking a median of 2.9 months. See every solar farm decision in Mid Devon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 18 | 10.4 km |
Solar Photovoltaics · Under Construction | 5 | 12.3 km |
Solar Photovoltaics · Operational | 3.1 | 12.5 km |
Solar Photovoltaics · Operational | 1.8 | 13.3 km |
Anaerobic Digestion · Operational | 2 | 13.7 km |
Solar Photovoltaics · Operational | 5 | 13.8 km |
Solar Photovoltaics · Operational | 1.1 | 13.9 km |
Solar Photovoltaics · Operational | 5 | 13.9 km |
How big is West Bradley Farm?
West Bradley Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates West Bradley Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was West Bradley Farm approved and built?
The application was submitted on 16 March 2012. Permission was granted on 18 May 2012, 2 months later. The site became operational on 3 August 2012, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1445.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode