Novarly ParcelRenewable sites

Renewable sitesBatsworthy Cross

Batsworthy Cross

Batsworthy Cross is operational in North Devon with a recorded capacity of 18 MW, and has been generating since 2016-04-07.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-04-07
Wind Onshore
Technology
Blackrock Real Assets
North Devon
Authority
England

Planning and build timeline

Application submitted2006-11-18
Permission granted2012-10-22
71 months after submission
Operational2016-04-07
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Devon’s record on onshore wind

North Devon has decided 6 onshore wind schemes and approved 33%, taking a median of 26.1 months. See every onshore wind scheme decision in North Devon

Other built sites within 15 km

SiteMWDistance
Bommertown Solar Farm
Solar Photovoltaics · Operational
55.3 km
Great Hele Farm AD farm waste
Anaerobic Digestion · Operational
1.310.2 km
West Bradley Farm
Solar Photovoltaics · Operational
1.510.4 km
Kingsland Barton Solar Farm
Solar Photovoltaics · Operational
513.4 km
Broadgate Solar Farm
Solar Photovoltaics · Operational
1.113.7 km

How big is Batsworthy Cross?

Batsworthy Cross has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Batsworthy Cross?

REPD records the operator as Blackrock Real Assets. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Batsworthy Cross approved and built?

The application was submitted on 2006-11-18. Permission was granted on 2012-10-22, 71 months later. The site became operational on 2016-04-07, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4057.

Novarly Parcel · official public data, read properly · parcel.novarly.com