Stoneshill Farm is operational in Mid Devon with a recorded capacity of 5 MW, and has been generating since 2017-03-17.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-17
Solar Photovoltaics
Technology
Green Energy UK Direct
Mid Devon
Authority
England

Planning and build timeline

Application submitted2014-11-21
Permission granted2016-02-05
14 months after submission
Operational2017-03-17
13 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Mid Devon’s record on solar

Mid Devon has decided 30 solar farms and approved 80%, taking a median of 2.9 months. See every solar farm decision in Mid Devon

Other built sites within 15 km

SiteMWDistance
Willand AD
Anaerobic Digestion · Operational
21.6 km
Nether Mill Farm
Solar Photovoltaics · Operational
3.12.5 km
Langlands Solar Farm
Solar Photovoltaics · Operational
2.12.7 km
Little Toms - Solar Farm
Solar Photovoltaics · Under Construction
52.8 km
Kia Ora Farm
Solar Photovoltaics · Operational
1.83.1 km
Higher Pirzwell Solar Farm
Solar Photovoltaics · Operational
1.24.9 km
Winham Farm
Solar Photovoltaics · Operational
56.1 km
Langford Solar Farm
Solar Photovoltaics · Operational
356.2 km

How big is Stoneshill Farm?

Stoneshill Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stoneshill Farm?

REPD records the operator as Green Energy UK Direct. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stoneshill Farm approved and built?

The application was submitted on 2014-11-21. Permission was granted on 2016-02-05, 14 months later. The site became operational on 2017-03-17, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4794.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council