Solar planning in Mid Devon
Mid Devon has decided 30 solar farms and approved 80% of them, taking a median of 2.9 months to decide. Consented capacity: 133 MW. 7 applications still awaiting a decision.
How Mid Devon compares
Against the 298 UK authorities with 5+ solar decisions, Mid Devon sits in the 7th percentile for approval rate (13 points below the England average) and the 36th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (41)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Homeleigh - Solar Photovoltaics Panels Frank Clarke & Sons Limited · 25/01058/PNSOL · 1.3 mo to decide | 0.17 | Awaiting Construction | 2025-09-08 |
Clannaborough Barton, Bow - Solar Panels Private Developer · 25/00125/PNSOL · 1.7 mo to decide | 0.16 | Awaiting Construction | 2025-03-28 |
Broad Path - Solar Panels Valencia Energy Limited · DCC/4419/2024 | 4.3 | Application Submitted | 2025-01-13 |
Little Toms - Solar Farm PS Renewables · 23/01838/MFUL · 6.7 mo to decide | 5 | Under Construction | 2024-06-20 |
Heathcoat Fabrics Limited, West-Exe North - Solar Panels Heathcoat Fabrics Limited · 24/00550/PNSOL · 1.8 mo to decide | 0.26 | Awaiting Construction | 2024-06-03 |
Dean Hill Road - Solar Farm Low Carbon Storage Ireland · 22/02374/MFUL · 10.8 mo to decide | 49.9 | Awaiting Construction | 2023-11-30 |
Petroc College, Bolham Road - Solar Petroc · 23/00991/PNSOL� · 2.9 mo to decide | 0.44 | Awaiting Construction | 2023-10-05 |
Petroc College, Bolham Road - Solar, Battery & Ground Source Heat Pump Petroc · 23/00728/CLP | 0.44 | Revised | 2023-04-27 |
Langford Solar Farm JBM Solar Projects · 19/01679/MFUL · 37.8 mo to decide | 35 | Operational | 2022-12-05 |
Lords Meadow Leisure Centre - Solar Photovoltaic Panels Mid Devon District Council · 22/01554/MFUL · 2.3 mo to decide | — | Awaiting Construction | 2022-11-10 |
Hepco Slide Systems Roof PV Hepco Slide Systems Limited · 21/00867/PNSOL · 1.8 mo to decide | 0.19 | Awaiting Construction | 2021-06-30 |
Heathcoat Fabrics Limited Heathcoat Fabrics Limited · 21/00253/PNSOL · 2.9 mo to decide | 0.19 | Awaiting Construction | 2021-04-07 |
Stoneshill Farm Green Energy UK Direct · 14/01949/MFUL · 14.5 mo to decide | 5 | Operational | 2016-02-05 |
Broadpath Landfill Viridor · 15/01511/MFUL · 2.6 mo to decide | 5 | Abandoned | 2015-12-18 |
Dunscombe Solar Elgin Energy · 15/01194/MFUL · 4.1 mo to decide | 5 | Appeal Refused | 2015-12-11 |
Wiseburrow Farm Sum Farming UK · 15/01108/MFUL · 4.6 mo to decide | 6 | Appeal Refused | 2015-12-04 |
Sharland Solar Farm Lightsource Renewable Energy · 15/00537/MFUL · 3.3 mo to decide | 2.8 | Operational | 2015-07-08 |
West Holcombe Wessex Solar Energy · 14/01452/MFUL · 9.9 mo to decide | 5.5 | Under Construction | 2015-06-24 |
Red Hill Farm Lightsource Renewable Energy · 14/01984/MFUL · 2.6 mo to decide | 4.8 | Operational | 2015-02-13 |
Wiseburrow Farm Primrose Solar/Camborne Energy · 14/01932/MFUL� · 2.5 mo to decide | 6 | Revised | 2015-02-12 |
Stumpy Cross juwi Renewable Energies · 14/01501/MFUL · 3 mo to decide | 4.5 | Appeal Refused | 2014-12-05 |
Stoneshill Farm Green Energy UK Direct · 14/01248/MFUL | 6 | Revised | 2014-10-20 |
Great Curham Farm British Solar Renewables · 14/00889/MFUL · 2.9 mo to decide | 8 | Application Refused | 2014-08-29 |
West Holcombe Wessex Solar Energy · 14/00903/MFUL | 5.5 | Application Withdrawn | 2014-08-20 |
Winham Farm Hive Energy · 14/00536/MFUL · 2.9 mo to decide | 5 | Operational | 2014-07-04 |
Nether Mill Farm AEE Renewables · 12/01518/MFUL · 15.6 mo to decide | 3.1 | Operational | 2014-02-19 |
Venn Farm EBS Energy LLP · 13/01416/MFUL · 3.8 mo to decide | 1 | Abandoned | 2014-02-07 |
Winham Farm Hive Energy · 13/01408/MFUL | 5 | Revised | 2014-01-20 |
Buckhayes Farm Lumicity · 13/00185/MFUL · 6.5 mo to decide | 6 | Application Refused | 2013-08-21 |
Great Curham Farm Solar Power Generation Ltd · 12/01664/MFUL · 6.1 mo to decide | 6.3 | Revised | 2013-06-05 |
Keens Farm juwi Renewable Energies · 12/01522/MFUL · 3 mo to decide | 5.1 | Appeal Refused | 2013-02-06 |
Gratton Copse Wessex Solar Energy · 12/01195/MFUL | 5 | Application Withdrawn | 2013-01-18 |
Ellicombe Farm Lightsource Renewable Energy · 12/01306/MFUL · 3 mo to decide | 1.4 | Operational | 2012-12-13 |
Kia Ora Farm Lightsource Renewable Energy · 12/01350/MFUL · 2.4 mo to decide | 1.8 | Operational | 2012-11-30 |
Nether Mill Farm AEE Renewables · 12/01071/MFUL | 3.1 | Revised | 2012-10-02 |
Langlands Solar Farm Cetis · 12/00628/MFUL · 2.8 mo to decide | 2.1 | Operational | 2012-08-07 |
Barton Solar Farm Lightsource Renewable Energy · 12/00412/MFUL · 2.3 mo to decide | 1.2 | Operational | 2012-05-25 |
Broadgate Solar Farm Lightsource Renewable Energy · 12/00376/MFUL · 2.3 mo to decide | 1.1 | Operational | 2012-05-24 |
Higher Pirzwell Solar Farm Lightsource Renewable Energy · 12/00373/MFUL · 2.2 mo to decide | 1.2 | Operational | 2012-05-21 |
West Bradley Farm Lightsource Renewable Energy · 12/00415/MFUL · 2.1 mo to decide | 1.5 | Operational | 2012-05-18 |
Ayshford Court Farm AEE Renewables · 10/01930/MFUL · 5.3 mo to decide | 5 | Operational | 2011-06-03 |
Does Mid Devon approve solar farms?
Yes — of the 30 solar farms Mid Devon has decided, 80% were approved (24 granted, 6 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Mid Devon?
The median time from application to decision is 2.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Mid Devon consented?
133 MW has been consented across 24 approved schemes, with 35 MW refused. A further 7 applications awaits a decision.
Other technologies in Mid Devon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.