Bommertown Solar Farm is an operational 5 MW solar farm in North Devon, generating since 16 December 2015. Planning permission was granted on 5 August 2014, 24 months after submission. Operator of record: Steadfast Molland Solar Ltd.
Planning and build timeline
| Application submitted | 30 July 2012 |
| Permission granted | 5 August 2014 24 months after submission |
| Operational | 16 December 2015 16 months after consent |
Screening a site of your own?
North Devon approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bommertown Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Devon’s record on solar
North Devon has decided 23 solar farms and approved 96%, taking a median of 4.9 months. See every solar farm decision in North Devon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 18 | 5.3 km |
Anaerobic Digestion · Operational | 1.3 | 9.9 km |
Solar Photovoltaics · Operational | 5 | 12.7 km |
Solar Photovoltaics · Operational | 1.5 | 13.9 km |
How big is Bommertown Solar Farm?
Bommertown Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bommertown Solar Farm?
REPD records the operator as Steadfast Molland Solar Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bommertown Solar Farm approved and built?
The application was submitted on 30 July 2012. Permission was granted on 5 August 2014, 24 months later. The site became operational on 16 December 2015, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2101.