Novarly ParcelRenewable sites

Renewable sitesGammaton Moor Solar farm

Gammaton Moor Solar farm

Gammaton Moor Solar farm is a 32 MW solar farm under construction in Torridge. Planning permission was granted on 19 April 2022, 8 months after submission. Operator of record: Lightsource SPV 175 Limited.

32 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Lightsource SPV 175 Limited
Torridge
Authority
England

Planning and build timeline

Application submitted1 September 2021
Permission granted19 April 2022
8 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Torridge approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Gammaton Moor Solar farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on solar

Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.70.3 km
Solar Photovoltaics · Operational
3.52.7 km
Solar Photovoltaics · Operational
0.153.7 km
Wind Onshore · Operational
2.64.1 km
Solar Photovoltaics · Operational
49.94.5 km
Landfill Gas · Operational
24.8 km
Solar Photovoltaics · Operational
25.3 km
Solar Photovoltaics · Operational
4.55.4 km

How big is Gammaton Moor Solar farm?

Gammaton Moor Solar farm has a recorded installed capacity of 32 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gammaton Moor Solar farm?

REPD records the operator as Lightsource SPV 175 Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gammaton Moor Solar farm approved and built?

The application was submitted on 1 September 2021. Permission was granted on 19 April 2022, 8 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9785.