Renewable sitesGoonabarn Farm Wind Turbines

Goonabarn Farm Wind Turbines

Goonabarn Farm Wind Turbines is an operational 1 MW onshore wind farm in Cornwall, generating since 1 April 2016. Planning permission was granted on 4 July 2013, 5 months after submission. Operator of record: George Richards Farms Partnership.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2016
Wind Onshore
Technology
George Richards Farms Partnership
Cornwall
Authority
England

Planning and build timeline

Application submitted12 February 2013
Permission granted4 July 2013
5 months after submission
Operational1 April 2016
33 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 74% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Goonabarn Farm Wind Turbines’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
101.6 km
Solar Photovoltaics · Operational
51.9 km
Solar Photovoltaics · Operational
52.3 km
Solar Photovoltaics · Operational
1.12.6 km
Solar Photovoltaics · Operational
73 km
Solar Photovoltaics · Operational
1.53 km
Solar Photovoltaics · Operational
124 km
Solar Photovoltaics · Operational
4.84.4 km

How big is Goonabarn Farm Wind Turbines?

Goonabarn Farm Wind Turbines has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Goonabarn Farm Wind Turbines?

REPD records the operator as George Richards Farms Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Goonabarn Farm Wind Turbines approved and built?

The application was submitted on 12 February 2013. Permission was granted on 4 July 2013, 5 months later. The site became operational on 1 April 2016, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3918.