Renewable sitesBurthy Farm

Burthy Farm

Burthy Farm is operational in Cornwall with a recorded capacity of 10 MW, and has been generating since 2015-03-20.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-20
Solar Photovoltaics
Technology
Elgin Energy EsCo
Cornwall
Authority
England

Planning and build timeline

Application submitted2013-07-12
Permission granted2014-09-30
15 months after submission
Operational2015-03-20
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Trefullock Solar Farm
Solar Photovoltaics · Operational
51 km
Summercourt Solar Farm (Glebe Farm)
Solar Photovoltaics · Operational
1.11.6 km
Goonabarn Farm Wind Turbines
Wind Onshore · Operational
11.6 km
Land North East Of Penrose Far
Solar Photovoltaics · Operational
1.51.9 km
Hewas Solar Farm
Solar Photovoltaics · Operational
52.4 km
KERNICK MICA DAM - SOLAR FARM
Solar Photovoltaics · Operational
123.1 km
Trethosa Farm Solar Park
Solar Photovoltaics · Operational
4.83.4 km
Carnemough Farm Solar Park
Solar Photovoltaics · Operational
73.5 km

How big is Burthy Farm?

Burthy Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burthy Farm?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burthy Farm approved and built?

The application was submitted on 2013-07-12. Permission was granted on 2014-09-30, 15 months later. The site became operational on 2015-03-20, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1718.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council