Renewable planning Onshore windSouth Ayrshire

Onshore wind planning in South Ayrshire

South Ayrshire has decided 12 onshore wind schemes and approved 33% of them, taking a median of 24.6 months to decide. Consented capacity: 106 MW. 3 applications still awaiting a decision.

33%
Approved
4 granted · 8 refused
24.6 mo
Median decision
UK 11.5 mo
106 MW
Consented
140 MW refused
8
Appeals
3 allowed on appeal

How South Ayrshire compares

Against the 75 UK authorities with 5+ onshore wind decisions, South Ayrshire sits in the 6th percentile for approval rate (35 points below the England average) and the 11th percentile for speed.

Decisions by year

35Approved — 1 (2013)Refused — 1 (2013)213Approved — 1 (2014)Refused — 2 (2014)314Approved — 1 (2015)Refused — 1 (2015)215Approved — 1 (2017)Refused — 2 (2017)317Refused — 1 (2019)119Refused — 1 (2024)124
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (16)

SchemeMWStatusDecided
Olympic Business Park, Dundonald - 2 Wind Turbines
The Farm Energy Partnership · 24/00063/APP · 10.5 mo to decide
8.52Application Refused2024-12-16
Ladywell Avenue - Wind Turbine
Land Energy Girvan Limited · 23/00816/APP
1Application Submitted2023-12-24
Ailsa Hospital - Wind Turbine
NHS Ayrshire & Arran · 22/00625/APP
1Application Submitted2022-07-29
Millenderdale Wind Farm
GreenPower (International) Ltd · 14/00764/APPM · 56.6 mo to decide
15Appeal Refused2019-03-06
Altercannoch Wind Farm
Brookfield Renewable UK · 22.8 mo to decide
27.7Appeal Refused2017-11-16
Knockskae Wind Farm
PNE Wind UK · 15/01216/APPM · 17.5 mo to decide
25.3Application Refused2017-04-19
Kirk Hill Wind Farm
Corolis Energy/ ESB / Ripple Energy · 14/01646/APPM · 24.6 mo to decide
18.8Operational2017-02-16
Straid Farm Wind Park
Ecotricity · 12/00090/APPM · 45.4 mo to decide
36.8Appeal Refused2015-05-13
Dalquhandy Windfarm
Dalquhandy Wind Farm Limited · CL/12/0042 · 35.8 mo to decide
42Operational2015-01-27
Breaker Hill
Wind Prospect Developments · 13/01310/APP · 6.7 mo to decide
7.2Appeal Refused2014-06-19
Chapelton Farm
Private Developer · 13/01506/APP · 3.5 mo to decide
2.6Application Refused2014-05-01
Tralorg Wind Farm
RPMI Railpen (formerly BayWa) · 11/01569/APPM · 36.4 mo to decide
20Operational2014-02-21
Assel Valley Wind Farm
Falck Renewables · 11/00564/APPM · 27.1 mo to decide
25Operational2013-09-03
Corwar Wind Farm
Willowind Developments · 12/01384/APP · 8.6 mo to decide
16.4Appeal Refused2013-08-30
Breaker Hill
Wind Prospect · 09/00979/APP · 30.3 mo to decide
19.5Revised2012-03-15
Knoweside Hill
H J Banks and Co Ltd
19.5Application Withdrawn2011-09-27

Does South Ayrshire approve onshore wind schemes?

Yes — of the 12 onshore wind schemes South Ayrshire has decided, 33% were approved (4 granted, 8 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in South Ayrshire?

The median time from application to decision is 24.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has South Ayrshire consented?

106 MW has been consented across 4 approved schemes, with 140 MW refused. A further 3 applications awaits a decision.

Other technologies in South Ayrshire

Solar in South AyrshireBattery storage in South Ayrshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.