Solar planning in Doncaster

Doncaster has decided 27 solar farms and approved 96% of them, taking a median of 2.3 months to decide. Consented capacity: 217 MW. 4 applications still awaiting a decision.

96%
Approved
26 granted · 1 refused
2.3 mo
Median decision
UK 2.3 mo
217 MW
Consented
40 MW refused
0
Appeals
no appeals recorded

How Doncaster compares

Against the 298 UK authorities with 5+ solar decisions, Doncaster sits in the 47th percentile for approval rate (3 points above the England average) and the 51st percentile for speed.

Decisions by year

510Approved — 2 (2014)214Approved — 1 (2015)115Approved — 1 (2016)116Approved — 1 (2019)119Approved — 3 (2021)321Approved — 4 (2022)422Approved — 7 (2023)723Approved — 2 (2024)224Approved — 3 (2025)Refused — 1 (2025)425Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (31)

SchemeMWStatusDecided
Premier Logistics Park, Churchill Road - Solar PV Panels
Fit Out Uk Limited · 25/02407/PRIOR · 1.8 mo to decide
Awaiting Construction2026-02-02
Marr Hall Farm, Barnsley Road - Solar Farm
Enviromena Asset Management UK Limited · 23/02634/FULM · 23.1 mo to decide
40Application Refused2025-12-19
Don Valley Academy, Jossey Lane - Solar PV Panels
Delta Academies Trust · 25/02069/PRIOR · 1.6 mo to decide
0.3Awaiting Construction2025-12-05
Butt Lane, Hooton Pagnell - Solar Farm
British Solar Renewables · 25/02389/FULM
49.9Application Submitted2025-12-05
De Warenne Academy, Gardens Lane - Solar panels
Solar Options for Schools Limited · 25/02169/PRIOR · 1.7 mo to decide
0.24Awaiting Construction2025-12-02
Moorhouse Grange, Moorhouse Lane - Solar Farm
Zetland Group · 25/01535/FULM
30Application Submitted2025-08-22
Aggreko UK, Sandall Stones Road - Solar PV
Aggreko UK Limited · 25/00936/FUL · 2.6 mo to decide
0.23Awaiting Construction2025-07-31
The Balk, Almholme - Solar Farm
Innova Renewables · 23/02482/FULM · 10.5 mo to decide
49.9Awaiting Construction2024-10-14
Morris And Co Handlers, Balby Carr Bank - Solar Pv Panels
Morris & Co Handlers Limited · 23/02271/PRIOR · 1.8 mo to decide
0.27Awaiting Construction2024-01-03
Yorkshire Way, Armthorpe - Solar Array
Maersk Logistics And Services UK Limited · 23/01970/PRIOR · 1.2 mo to decide
0.99Awaiting Construction2023-11-09
Jj Foodservice Limited, Derbyshire Court - Solar Panels
JJ Foodservice Limited · 23/01497/PRIOR · 1.3 mo to decide
0.2Awaiting Construction2023-08-29
Doncaster Road, Doncaster Road - Solar Array
M&T Haylage · 22/02528/FULM · 6.9 mo to decide
1.03Awaiting Construction2023-06-28
Croft Farm, Askern Road - Solar Array & Hydrogen Plant
CF Estates (Yorkshire) Limited · 22/02088/FULM · 7.9 mo to decide
2.5Under Construction2023-05-11
Mere Flats Solar Farm
NextPower UK · 22/01978/FULM · 8.3 mo to decide
56Awaiting Construction2023-05-03
Morris & Co Handlers, Balby Carr Bank - Solar Panels
Morris & Co Handlers Limited · 23/00145/PRIOR · 1.8 mo to decide
0.64Awaiting Construction2023-04-03
Haith Group Limited, Cow House Lane - Solar Panels
Haith Group Limited · 23/00193/PRIOR · 1.3 mo to decide
0.2Awaiting Construction2023-03-13
Red House Farm, High Melton -Solar Panels
Private Developer · 22/01274/PRIOR · 3.9 mo to decide
0.16Awaiting Construction2022-09-13
Tudworth Field Road, Hatfield - Solar Panels
SJS Agriplant Limited · 22/00698/FUL · 3.2 mo to decide
0.18Under Construction2022-07-06
Tudworth Field Road, Hatfield - Solar PV Panels
SJS Agriplant Limited · 22/00699/FUL · 0.2 mo to decide
0.27Operational2022-04-05
Eland House, Denaby - Solar Panels
Eland Cables Limited · 22/00920/PRIOR
0.33Application Submitted2022-04-05
Warren Farm Solar Farm & Battery Storage
Enso Green Holdings I Limited · 21/02567/FULM · 6.9 mo to decide
49.9Awaiting Construction2022-03-15
Red House Farm, High Melton - Red House Solar Panels
Private Developer · 21/02151/PRIOR · 2.1 mo to decide
0.15Awaiting Construction2021-09-03
Toronto Way, New Rossington Solar Panels
Sonne Solar Limited · 21/00377/FULM · 2 mo to decide
2.3Awaiting Construction2021-04-08
Iport Avenue, New Rossington Solar Panels
Sonne Solar Limited · 21/00376/FULM · 1.7 mo to decide
1.9Awaiting Construction2021-03-29
Amazon LBA2 (Principal Place)
Amazon UK Services / Push Energy · 18/01797/FULM · 8.3 mo to decide
2Planning Permission Expired2019-03-28
Partridge Hill Solar Farm
Green Switch Solutions/Belvedere Energy Developments · 15/01268/FULM · 14.3 mo to decide
33Awaiting Construction2016-07-29
Thorne Farm
Conergy · 14/01554/FULM · 7.1 mo to decide
5Operational2015-04-16
Askern Colliery solar farm
Anesco · 14/01829/FULM · 4.2 mo to decide
5Operational2014-12-08
Ikea Distribution Centre
IKEA Properties Investments Ltd · 14/00366/FUL · 1.6 mo to decide
1.7Operational2014-04-08
Ikea Distribution Centre
IKEA Properties Investments Ltd · 13/02025/FUL
2Revised2013-11-25
Next Distribution Centre Doncaster
Next/ Eneco
2.5Operational

Does Doncaster approve solar farms?

Yes — of the 27 solar farms Doncaster has decided, 96% were approved (26 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Doncaster?

The median time from application to decision is 2.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Doncaster consented?

217 MW has been consented across 26 approved schemes, with 40 MW refused. A further 4 applications awaits a decision.

Other technologies in Doncaster

Battery storage in DoncasterOnshore wind in Doncaster

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.