Novarly ParcelRenewable sites

Renewable sitesLow Spinney Wind Farm

Low Spinney Wind Farm

Low Spinney Wind Farm is an operational 8 MW onshore wind farm in Harborough, generating since 29 September 2011. Planning permission was granted on 3 September 2009, 7 months after submission. Operator of record: Infinis, previously Broadview Energy Developments.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 29 September 2011
Wind Onshore
Technology
Infinis, previously Broadview Energy Developments
Harborough
Authority
England

Planning and build timeline

Application submitted11 February 2009
Permission granted3 September 2009
7 months after submission
Operational29 September 2011
25 months after consent

Screening a site of your own?

RedlineUK · £39

Harborough approves 40% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Low Spinney Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Harborough’s record on onshore wind

Harborough has decided 5 onshore wind schemes and approved 40%, taking a median of 3.9 months. See every onshore wind scheme decision in Harborough

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.57.8 km
Solar Photovoltaics · Operational
268 km
Landfill Gas · Operational
2.78.5 km
Solar Photovoltaics · Operational
18.38.6 km
Landfill Gas · Operational
2.39.1 km
Wind Onshore · Operational
2210.1 km
Anaerobic Digestion · Operational
2.510.1 km
Solar Photovoltaics · Under Construction
2010.2 km

How big is Low Spinney Wind Farm?

Low Spinney Wind Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Low Spinney Wind Farm?

REPD records the operator as Infinis, previously Broadview Energy Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Low Spinney Wind Farm approved and built?

The application was submitted on 11 February 2009. Permission was granted on 3 September 2009, 7 months later. The site became operational on 29 September 2011, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3682.