Renewable sites › Stowbridge Farm - Extension (Phase 2)
Stowbridge Farm - Extension (Phase 2)
Stowbridge Farm - Extension (Phase 2) is an operational 10 MW solar farm in East Cambridgeshire, generating since 20 March 2015. Planning permission was granted on 11 November 2014, 3 months after submission. Operator of record: FC Palmer and Sons.
Planning and build timeline
| Application submitted | 30 July 2014 |
| Permission granted | 11 November 2014 3 months after submission |
| Operational | 20 March 2015 4 months after consent |
Screening a site of your own?
East Cambridgeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Stowbridge Farm - Extension (Phase 2)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Cambridgeshire’s record on solar
East Cambridgeshire has decided 21 solar farms and approved 100%, taking a median of 3.4 months. See every solar farm decision in East Cambridgeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 10 | 0.3 km |
Solar Photovoltaics · Operational | 24 | 0.7 km |
Solar Photovoltaics · Operational | 5 | 1.7 km |
Solar Photovoltaics · Operational | 6.3 | 2.1 km |
Solar Photovoltaics · Operational | 5 | 4.2 km |
Solar Photovoltaics · Operational | 19.3 | 4.7 km |
Solar Photovoltaics · Operational | 1.1 | 5 km |
Solar Photovoltaics · Under Construction | 29.4 | 6.3 km |
How big is Stowbridge Farm - Extension (Phase 2)?
Stowbridge Farm - Extension (Phase 2) has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Stowbridge Farm - Extension (Phase 2)?
REPD records the operator as FC Palmer and Sons. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stowbridge Farm - Extension (Phase 2) approved and built?
The application was submitted on 30 July 2014. Permission was granted on 11 November 2014, 3 months later. The site became operational on 20 March 2015, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2218.