Chittering Solar Farm

Chittering Solar Farm is operational in South Cambridgeshire with a recorded capacity of 5 MW, and has been generating since 2012-06-28.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-06-28
Solar Photovoltaics
Technology
Abbey Renewables
South Cambridgeshire
Authority
England

Planning and build timeline

Application submitted2010-12-15
Permission granted2011-03-15
3 months after submission
Operational2012-06-28
15 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Cambridgeshire’s record on solar

South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire

Other built sites within 15 km

SiteMWDistance
Chittering Solar Farm Extension
Solar Photovoltaics · Operational
6.30.4 km
Stowbridge Farm
Solar Photovoltaics · Operational
241.2 km
Stowbridge Farm - Extension (Phase 1)
Solar Photovoltaics · Operational
101.5 km
Stowbridge Farm - Extension (Phase 2)
Solar Photovoltaics · Operational
101.7 km
Ely Road Waste Management Park
Solar Photovoltaics · Operational
1.13.6 km
Mingay Farm - extension
Solar Photovoltaics · Operational
19.34.8 km
Mingay Farm
Solar Photovoltaics · Operational
54.8 km
North Angle Farm
Solar Photovoltaics · Under Construction
29.46.5 km

How big is Chittering Solar Farm?

Chittering Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chittering Solar Farm?

REPD records the operator as Abbey Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chittering Solar Farm approved and built?

The application was submitted on 2010-12-15. Permission was granted on 2011-03-15, 3 months later. The site became operational on 2012-06-28, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1553.