Renewable sitesStonehill Energy Storage / Lower Minety

Stonehill Energy Storage / Lower Minety

Stonehill Energy Storage / Lower Minety is an operational 50 MW battery storage site in Wiltshire, generating since 15 December 2022. Planning permission was granted on 7 February 2020, 2 months after submission. Operator of record: Penso Power (BW ESS).

50 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2022
Battery
Technology
Penso Power (BW ESS)
Wiltshire
Authority
England

Planning and build timeline

Application submitted29 November 2019
Permission granted7 February 2020
2 months after submission
Operational15 December 2022
34 months after consent

Screening a site of your own?

RedlineUK · £39

Wiltshire approves 97% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Stonehill Energy Storage / Lower Minety’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on battery storage

Wiltshire has decided 30 battery storage schemes and approved 97%, taking a median of 13.9 months. See every battery storage scheme decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Battery · Operational
500 km
Battery · Operational
500 km
Battery · Operational
49.990.5 km
Battery · Operational
49.991.2 km
Solar Photovoltaics · Operational
14.53.7 km
Solar Photovoltaics · Operational
8.75.1 km
Solar Photovoltaics · Operational
49.96.4 km
Solar Photovoltaics · Operational
87.3 km

How big is Stonehill Energy Storage / Lower Minety?

Stonehill Energy Storage / Lower Minety has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stonehill Energy Storage / Lower Minety?

REPD records the operator as Penso Power (BW ESS). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stonehill Energy Storage / Lower Minety approved and built?

The application was submitted on 29 November 2019. Permission was granted on 7 February 2020, 2 months later. The site became operational on 15 December 2022, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7773.