St Francis Court Farm
St Francis Court Farm is operational in East Devon with a recorded capacity of 4 MW, and has been generating since 2017-02-01.
Planning and build timeline
| Application submitted | 2013-11-29 |
| Permission granted | 2014-05-07 5 months after submission |
| Operational | 2017-02-01 33 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Devon’s record on solar
East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burrowton Farm Solar Photovoltaics · Operational | 5 | 3.2 km |
Crannaford Solar Farm Solar Photovoltaics · Operational | 12.5 | 4.4 km |
SAUNDERCROFT SOLAR FARM Solar Photovoltaics · Operational | 7 | 4.7 km |
Enfield Farm Anaerobic Digestion · Operational | 2 | 6.8 km |
STRETE FARM SOLAR FARM Solar Photovoltaics · Operational | 4.8 | 7.9 km |
Winham Farm Solar Photovoltaics · Operational | 5 | 8 km |
Exeter EfW EfW Incineration · Operational | 13 | 8.1 km |
Ford Oaks Solar & Green Infrastructure Facility Solar Photovoltaics · Under Construction | 30 | 8.3 km |
How big is St Francis Court Farm?
St Francis Court Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates St Francis Court Farm?
REPD records the operator as Martifer Solar (Voltalia). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was St Francis Court Farm approved and built?
The application was submitted on 2013-11-29. Permission was granted on 2014-05-07, 5 months later. The site became operational on 2017-02-01, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2145.