Renewable sitesFord Oaks Solar & Green Infrastructure Facility

Ford Oaks Solar & Green Infrastructure Facility

Ford Oaks Solar & Green Infrastructure Facility is a 30 MW solar farm under construction in East Devon. Planning permission was granted on 30 November 2023, 18 months after submission. Operator of record: Low Carbon Alliance / Taiyo Power & Storage.

30 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Low Carbon Alliance / Taiyo Power & Storage
East Devon
Authority
England

Planning and build timeline

Application submitted19 May 2022
Permission granted30 November 2023
18 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

East Devon approves 87% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ford Oaks Solar & Green Infrastructure Facility’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
100.6 km
Solar Photovoltaics · Operational
4.81.4 km
Solar Photovoltaics · Operational
12.54.3 km
Solar Photovoltaics · Operational
74.5 km
Anaerobic Digestion · Operational
14.8 km
Solar Photovoltaics · Operational
55.3 km
Anaerobic Digestion · Operational
26.3 km
Solar Photovoltaics · Under Construction
498.2 km

How big is Ford Oaks Solar & Green Infrastructure Facility?

Ford Oaks Solar & Green Infrastructure Facility has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ford Oaks Solar & Green Infrastructure Facility?

REPD records the operator as Low Carbon Alliance / Taiyo Power & Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ford Oaks Solar & Green Infrastructure Facility approved and built?

The application was submitted on 19 May 2022. Permission was granted on 30 November 2023, 18 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11366.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode