Burrowton Farm is operational in East Devon with a recorded capacity of 5 MW, and has been generating since 2016-09-18.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-18
Solar Photovoltaics
Technology
NextEnery Solar Fund (NESF)
East Devon
Authority
England

Planning and build timeline

Application submitted2011-04-12
Permission granted2011-10-13
6 months after submission
Operational2016-09-18
59 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Crannaford Solar Farm
Solar Photovoltaics · Operational
12.51.1 km
SAUNDERCROFT SOLAR FARM
Solar Photovoltaics · Operational
71.6 km
St Francis Court Farm
Solar Photovoltaics · Operational
43.2 km
STRETE FARM SOLAR FARM
Solar Photovoltaics · Operational
4.84.7 km
Ford Oaks Solar & Green Infrastructure Facility
Solar Photovoltaics · Under Construction
305.3 km
Great Houndbeare Farm
Solar Photovoltaics · Operational
105.9 km
Enfield Farm
Anaerobic Digestion · Operational
26.1 km
Winham Farm
Solar Photovoltaics · Operational
57.2 km

How big is Burrowton Farm?

Burrowton Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burrowton Farm?

REPD records the operator as NextEnery Solar Fund (NESF). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burrowton Farm approved and built?

The application was submitted on 2011-04-12. Permission was granted on 2011-10-13, 6 months later. The site became operational on 2016-09-18, 59 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1978.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council