Renewable sitesMount Vernon Hospital - Solar Panels

Mount Vernon Hospital - Solar Panels

Mount Vernon Hospital - Solar Panels is an operational solar farm in Hillingdon, generating since 31 December 2021. Planning permission was granted on 1 November 2021, 3 months after submission. Operator of record: The Hillingdon Hospitals NHS Foundation Trust.

Capacity
as recorded in REPD
Operational
Status
since 31 December 2021
Solar Photovoltaics
Technology
The Hillingdon Hospitals NHS Foundation Trust
Hillingdon
Authority
England

Planning and build timeline

Application submitted23 July 2021
Permission granted1 November 2021
3 months after submission
Operational31 December 2021
2 months after consent

Screening a site of your own?

RedlineUK · £39

Hillingdon approves 89% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Mount Vernon Hospital - Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Hillingdon’s record on solar

Hillingdon has decided 18 solar farms and approved 89%, taking a median of 1.8 months. See every solar farm decision in Hillingdon

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.48.5 km
Solar Photovoltaics · Operational
0.299.6 km
Landfill Gas · Operational
110.7 km
Landfill Gas · Operational
110.7 km
Landfill Gas · Operational
7.510.8 km
Solar Photovoltaics · Operational
313.1 km
Battery · Operational
0.213.5 km
Solar Photovoltaics · Operational
1.713.5 km

How big is Mount Vernon Hospital - Solar Panels?

REPD does not record an installed capacity for Mount Vernon Hospital - Solar Panels.

Who operates Mount Vernon Hospital - Solar Panels?

REPD records the operator as The Hillingdon Hospitals NHS Foundation Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mount Vernon Hospital - Solar Panels approved and built?

The application was submitted on 23 July 2021. Permission was granted on 1 November 2021, 3 months later. The site became operational on 31 December 2021, 2 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9467.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode