Renewable sites › St Johns Wells Wind Cluster Extension
St Johns Wells Wind Cluster Extension
St Johns Wells Wind Cluster Extension is operational in Aberdeenshire with a recorded capacity of 3.2 MW, and has been generating since 2015-03-01.
Planning and build timeline
| Application submitted | 2010-01-11 |
| Permission granted | 2012-06-22 29 months after submission |
| Operational | 2015-03-01 32 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Denhill Wind Onshore · Operational | 2.3 | 0.9 km |
St John's Well Wind Onshore · Operational | 2.4 | 1.1 km |
Haddo Wind Onshore · Operational | 4.6 | 2 km |
Courtstone Wind Turbine Wind Onshore · Operational | 2.3 | 5.3 km |
Mackies Dairy PV Solar Photovoltaics · Operational | 1.8 | 5.5 km |
Methlick Farmers Wind Energy Project Wind Onshore · Operational | 12 | 5.6 km |
Hill of Easterton Extension Wind Onshore · Operational | 2 | 5.8 km |
Hill of Easterton Wind Onshore · Operational | 2.5 | 5.8 km |
How big is St Johns Wells Wind Cluster Extension?
St Johns Wells Wind Cluster Extension has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates St Johns Wells Wind Cluster Extension?
REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was St Johns Wells Wind Cluster Extension approved and built?
The application was submitted on 2010-01-11. Permission was granted on 2012-06-22, 29 months later. The site became operational on 2015-03-01, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3840.