Hill of Balquhindachy extension
Hill of Balquhindachy extension is operational in Aberdeenshire with a recorded capacity of 1.7 MW, and has been generating since 2010-07-09.
Planning and build timeline
| Application submitted | 2007-03-20 |
| Permission granted | 2008-09-09 18 months after submission |
| Operational | 2010-07-09 22 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Methlick Farmers Wind Energy Project Wind Onshore · Operational | 12 | 5 km |
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm Wind Onshore · Operational | 6.9 | 5 km |
Haddo Wind Onshore · Operational | 4.6 | 6.3 km |
Skelmonae Wind Farm Wind Onshore · Operational | 3.2 | 6.5 km |
St John's Well Wind Onshore · Operational | 2.4 | 7.2 km |
St Johns Wells Wind Cluster Extension Wind Onshore · Operational | 3.2 | 8.3 km |
Courtstone Wind Turbine Wind Onshore · Operational | 2.3 | 9 km |
Denhill Wind Onshore · Operational | 2.3 | 9.1 km |
How big is Hill of Balquhindachy extension?
Hill of Balquhindachy extension has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hill of Balquhindachy extension?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hill of Balquhindachy extension approved and built?
The application was submitted on 2007-03-20. Permission was granted on 2008-09-09, 18 months later. The site became operational on 2010-07-09, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2758.