Renewable sitesHill of Balquhindachy extension

Hill of Balquhindachy extension

Hill of Balquhindachy extension is operational in Aberdeenshire with a recorded capacity of 1.7 MW, and has been generating since 2010-07-09.

1.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-07-09
Wind Onshore
Technology
Private Developer
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2007-03-20
Permission granted2008-09-09
18 months after submission
Operational2010-07-09
22 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Methlick Farmers Wind Energy Project
Wind Onshore · Operational
125 km
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm
Wind Onshore · Operational
6.95 km
Haddo
Wind Onshore · Operational
4.66.3 km
Skelmonae Wind Farm
Wind Onshore · Operational
3.26.5 km
St John's Well
Wind Onshore · Operational
2.47.2 km
St Johns Wells Wind Cluster Extension
Wind Onshore · Operational
3.28.3 km
Courtstone Wind Turbine
Wind Onshore · Operational
2.39 km
Denhill
Wind Onshore · Operational
2.39.1 km

How big is Hill of Balquhindachy extension?

Hill of Balquhindachy extension has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill of Balquhindachy extension?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill of Balquhindachy extension approved and built?

The application was submitted on 2007-03-20. Permission was granted on 2008-09-09, 18 months later. The site became operational on 2010-07-09, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2758.