Noriker Power Staunch is an operational 20 MW battery storage site in Newcastle-under-Lyme, generating since 15 March 2017. Planning permission was granted on 19 May 2016, 2 months after submission. Operator of record: Hazel Capital/ Noriker Power.

20 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2017
Battery
Technology
Hazel Capital/ Noriker Power
Newcastle-under-Lyme
Authority
England

Planning and build timeline

Application submitted24 March 2016
Permission granted19 May 2016
2 months after submission
Operational15 March 2017
10 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Newcastle-under-Lyme: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Noriker Power Staunch’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1.93.9 km
Solar Photovoltaics · Operational
4.44.2 km
Battery · Operational
4.2 km
EfW Incineration · Operational
14.26.4 km
Solar Photovoltaics · Operational
2.58 km
Solar Photovoltaics · Operational
8.412.9 km
Landfill Gas · Operational
1.314.6 km

How big is Noriker Power Staunch?

Noriker Power Staunch has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Noriker Power Staunch?

REPD records the operator as Hazel Capital/ Noriker Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Noriker Power Staunch approved and built?

The application was submitted on 24 March 2016. Permission was granted on 19 May 2016, 2 months later. The site became operational on 15 March 2017, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6918.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode