Renewable sites › Noriker Power Staunch
Noriker Power Staunch
Noriker Power Staunch is operational in Newcastle-under-Lyme with a recorded capacity of 20 MW, and has been generating since 2017-03-15.
Planning and build timeline
| Application submitted | 2016-03-24 |
| Permission granted | 2016-05-19 2 months after submission |
| Operational | 2017-03-15 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
The Low Carbon Energy Generation Project at Keele University Wind Onshore · Operational | 1.9 | 3.9 km |
Keele University Battery · Operational | — | 4.2 km |
Keele University Solar Photovoltaics · Operational | 4.4 | 4.2 km |
Stoke-on-Trent EfW EfW Incineration · Operational | 14.2 | 6.4 km |
Screwfix Direct Solar Photovoltaics · Operational | 2.5 | 8 km |
Land at Heywood Grange Solar Photovoltaics · Operational | 8.4 | 12.9 km |
Meece Landfill Landfill Gas · Operational | 1.3 | 14.6 km |
How big is Noriker Power Staunch?
Noriker Power Staunch has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Noriker Power Staunch?
REPD records the operator as Hazel Capital/ Noriker Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Noriker Power Staunch approved and built?
The application was submitted on 2016-03-24. Permission was granted on 2016-05-19, 2 months later. The site became operational on 2017-03-15, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6918.
Novarly Parcel · official public data, read properly · parcel.novarly.com