Rudge Hill Farm is operational in Dorset with a recorded capacity of 1.5 MW, and has been generating since 2013-10-25.
Planning and build timeline
| Application submitted | 2012-03-20 |
| Permission granted | 2013-02-20 11 months after submission |
| Operational | 2013-10-25 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dorset’s record on solar
Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lowbrook Farm Anaerobic Digester (Farm AD) Anaerobic Digestion · Operational | 1.3 | 3.4 km |
Park Farm Solar Photovoltaics · Operational | 4 | 7.7 km |
Land at Stalbridge Park Solar Photovoltaics · Operational | 5 | 8.2 km |
Canada Farm Solar Photovoltaics · Operational | 8.3 | 10.3 km |
Land at Bowden Lane Solar Photovoltaics · Operational | 5 | 11.2 km |
Milborne Port Solar Farm Solar Photovoltaics · Operational | 4.2 | 12.1 km |
Court Farm Business Park, Road To Court Farm - Hydroelectric System Large Hydro · Operational | 10 | 12.4 km |
Littleton Solar Photovoltaics · Operational | 12.1 | 12.7 km |
How big is Rudge Hill Farm?
Rudge Hill Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rudge Hill Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rudge Hill Farm approved and built?
The application was submitted on 2012-03-20. Permission was granted on 2013-02-20, 11 months later. The site became operational on 2013-10-25, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1723.
Novarly Parcel · official public data, read properly · parcel.novarly.com