Renewable sitesMilborne Port Solar Farm

Milborne Port Solar Farm

Milborne Port Solar Farm is operational in Somerset with a recorded capacity of 4.2 MW, and has been generating since 2018-06-25.

4.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-06-25
Solar Photovoltaics
Technology
Big 60 Million
Somerset
Authority
England

Planning and build timeline

Application submitted2015-05-18
Permission granted2016-08-18
15 months after submission
Operational2018-06-25
22 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Land at Bowden Lane
Solar Photovoltaics · Operational
51.9 km
Land at Stalbridge Park
Solar Photovoltaics · Operational
55.1 km
Higher Hatherleigh Solar Farm
Solar Photovoltaics · Operational
3.57.8 km
Land at Sutor Farm
Solar Photovoltaics · Operational
58 km
Higher Hatherleigh Solar Farm extension
Solar Photovoltaics · Operational
1.58.2 km
Hook Valley Solar Park
Solar Photovoltaics · Operational
178.2 km
Sutton Montis Road Solar Park / Sutton Bridge Solar Farm
Solar Photovoltaics · Operational
5.48.8 km
Chilton Cantelo Solar Farm
Solar Photovoltaics · Operational
510.7 km

How big is Milborne Port Solar Farm?

Milborne Port Solar Farm has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Milborne Port Solar Farm?

REPD records the operator as Big 60 Million. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Milborne Port Solar Farm approved and built?

The application was submitted on 2015-05-18. Permission was granted on 2016-08-18, 15 months later. The site became operational on 2018-06-25, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5290.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council