Novarly ParcelRenewable sites

Renewable sitesRisley '4' Landfill Scheme

Risley '4' Landfill Scheme

Risley '4' Landfill Scheme is operational in Warrington with a recorded capacity of 5.9 MW, and has been generating since 1999-05-01.

5.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1999-05-01
Landfill Gas
Technology
Biffa
Warrington
Authority
England

Planning and build timeline

Application submitted1996-11-08
Permission granted1997-03-17
4 months after submission
Operational1999-05-01
25 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Risley Sets 13 & 14
Landfill Gas · Operational
2.10.2 km
Risley
Landfill Gas · Operational
20.2 km
Butchersfield Landfill Site
Landfill Gas · Operational
34.6 km
SAICA Paper Mill
Biomass (dedicated) · Operational
41.65.9 km
Whitehead Landfill
Landfill Gas · Operational
5.37.1 km
Warrington Home Solar Scheme
Solar Photovoltaics · Operational
5.38.5 km
Tesco Crab Tree Lane
Solar Photovoltaics · Operational
0.59.6 km
Atherton - Battery energy storage
Battery · Operational
3010 km

How big is Risley '4' Landfill Scheme?

Risley '4' Landfill Scheme has a recorded installed capacity of 5.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Risley '4' Landfill Scheme?

REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Risley '4' Landfill Scheme approved and built?

The application was submitted on 1996-11-08. Permission was granted on 1997-03-17, 4 months later. The site became operational on 1999-05-01, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 572.