Renewable sites › Redhall Industrial Estate
Redhall Industrial Estate
Redhall Industrial Estate is an operational 5 MW solar farm in East Riding of Yorkshire, generating since 8 August 2014. Planning permission was granted on 21 January 2013, 3 months after submission. Operator of record: Dodds Limited.
Planning and build timeline
| Application submitted | 22 October 2012 |
| Permission granted | 21 January 2013 3 months after submission |
| Operational | 8 August 2014 19 months after consent |
Screening a site of your own?
East Riding of Yorkshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Redhall Industrial Estate’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on solar
East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 7.5 | 4 km |
Wind Onshore · Operational | 17.1 | 6.1 km |
Wind Onshore · Operational | 7.5 | 6.7 km |
Wind Onshore · Operational | 10.2 | 6.7 km |
Wind Onshore · Operational | 9 | 11.2 km |
Landfill Gas · Operational | 2 | 12.3 km |
Landfill Gas · Operational | 1 | 12.3 km |
EfW Incineration · Operational | 3.2 | 12.5 km |
How big is Redhall Industrial Estate?
Redhall Industrial Estate has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Redhall Industrial Estate?
REPD records the operator as Dodds Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Redhall Industrial Estate approved and built?
The application was submitted on 22 October 2012. Permission was granted on 21 January 2013, 3 months later. The site became operational on 8 August 2014, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2019.
Novarly Parcel · official public data, read properly · parcel.novarly.com