Renewable sites › PROMISED LAND FARM
PROMISED LAND FARM
PROMISED LAND FARM is operational in St. Helens with a recorded capacity of 1 MW, and has been generating since 2014-10-22.
Planning and build timeline
| Application submitted | 2013-05-15 |
| Permission granted | 2013-10-15 5 months after submission |
| Operational | 2014-10-22 12 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — St. Helens
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Billinge Hill Quarry Landfill Scheme Landfill Gas · Operational | 1 | 1.5 km |
Holiday Moss Gas to Energy II Landfill Gas · Operational | 1.4 | 2.2 km |
Holiday Moss Landfill Gas Scheme Landfill Gas · Operational | 2.9 | 2.2 km |
Sanko Gosei Solar Panels Solar Photovoltaics · Operational | 0.5 | 6.7 km |
Unit 5 XL Business Park Battery · Under Construction | 49.9 | 7.3 km |
IBL Cold Stores - Solar Photovoltaics Panels Solar Photovoltaics · Operational | 0.8 | 7.8 km |
West Quarry Landfill Gas · Operational | 4.5 | 7.9 km |
Lathom (Pilkington Technical Centre) Solar Photovoltaics · Operational | 2.5 | 8.6 km |
How big is PROMISED LAND FARM?
PROMISED LAND FARM has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates PROMISED LAND FARM?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was PROMISED LAND FARM approved and built?
The application was submitted on 2013-05-15. Permission was granted on 2013-10-15, 5 months later. The site became operational on 2014-10-22, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3361.
Novarly Parcel · official public data, read properly · parcel.novarly.com