Priors Byne Farm

Priors Byne Farm is an operational 7.6 MW solar farm in Horsham, generating since 20 January 2016. Planning permission was granted on 15 April 2015, 16 months after submission. Operator of record: Gamma Solar Limited.

7.6 MW
Capacity
as recorded in REPD
Operational
Status
since 20 January 2016
Solar Photovoltaics
Technology
Gamma Solar Limited
Horsham
Authority
England

Planning and build timeline

Application submitted18 December 2013
Permission granted15 April 2015
16 months after submission
Operational20 January 2016
9 months after consent

Screening a site of your own?

RedlineUK · £39

Horsham approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Priors Byne Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Horsham’s record on solar

Horsham has decided 18 solar farms and approved 94%, taking a median of 3.8 months. See every solar farm decision in Horsham

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
101.5 km
Solar Photovoltaics · Operational
53.1 km
Battery · Operational
106.5 km
Landfill Gas · Operational
26.6 km
Solar Photovoltaics · Operational
1.110.2 km
Solar Photovoltaics · Operational
0.211 km
Battery · Under Construction
49.9911.1 km
Solar Photovoltaics · Operational
1.712.6 km

How big is Priors Byne Farm?

Priors Byne Farm has a recorded installed capacity of 7.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Priors Byne Farm?

REPD records the operator as Gamma Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Priors Byne Farm approved and built?

The application was submitted on 18 December 2013. Permission was granted on 15 April 2015, 16 months later. The site became operational on 20 January 2016, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1536.