Kings Barn Farm - Energy Barn is operational in Horsham with a recorded capacity of 10 MW, and has been generating since 2017-03-31.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-31
Battery
Technology
Anesco/ Green Hedge Energy UK
Horsham
Authority
England

Planning and build timeline

Application submitted2016-07-22
Permission grantednot recorded
Operational2017-03-31

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Horsham’s record on battery storage

Horsham has decided 5 battery storage schemes and approved 80%, taking a median of 6.1 months. See every battery storage scheme decision in Horsham

Other built sites within 15 km

SiteMWDistance
Horton Landfill Site
Landfill Gas · Operational
22.3 km
Halewick Lane, Sompting - Battery-based Energy Storage Facility
Battery · Under Construction
49.994.9 km
Ford Farm (Ashurst)
Solar Photovoltaics · Operational
105.9 km
Priors Byne Farm
Solar Photovoltaics · Operational
7.66.5 km
Land off Hooklands Lane
Solar Photovoltaics · Operational
58.5 km
ParkerSteel Shoreham Plant
Solar Photovoltaics · Operational
1.89.9 km
Land Parcel North of Goddards
Solar Photovoltaics · Operational
514.3 km

How big is Kings Barn Farm - Energy Barn?

Kings Barn Farm - Energy Barn has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kings Barn Farm - Energy Barn?

REPD records the operator as Anesco/ Green Hedge Energy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kings Barn Farm - Energy Barn approved and built?

The application was submitted on 2016-07-22. REPD does not record a grant date. The site became operational on 2017-03-31.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6916.